Home/ Projects/ Industrial Facility – Dubai South
Industrial

Industrial Logistics
Facility, Dubai South

A large-scale 35,000 m² logistics and warehousing hub adjacent to Al Maktoum International Airport — engineered for heavy industrial operations and delivered on a fast-track 14-month programme.

GFA35,000
Warehouses4 Units
Duration14 Months
LocationDubai South
StatusCompleted
DeliveredQ1 2024
Scroll

Built for Scale &
Heavy Operations

The Dubai South Industrial Logistics Facility is one of ANIB's most technically demanding projects — a purpose-built warehousing and logistics campus comprising four large-span warehouse units, office accommodation, truck marshalling yards, and a full infrastructure package. Strategically located adjacent to Al Maktoum International Airport in Dubai South Free Zone, the facility is designed to support heavy logistics, cold-chain operations, and last-mile distribution.

ANIB delivered the entire project on a fast-track 14-month EPC programme: civil and earthworks, structural steel portal frames, cladding envelope, concrete hardstanding, all MEP services including 11kV substation, fire suppression systems, and site-wide drainage and roadworks. The facility was handed over operational-ready, with tenants in occupation within 30 days of completion.

35,000 m² Under Roof4 clearspan warehouse units ranging from 5,000 to 12,000 m² each
Fast-Track 14 MonthsEPC lump-sum contract from site possession to full operational handover
JAFZA / Dubai South CompliantFull regulatory and authority approvals managed by ANIB in-house
11kV SubstationDedicated high-voltage electrical substation serving the full campus load
Contract ValueAED 38M EPC package inclusive of infrastructure, MEP, and civil works

Execution Approach

Phase 01
Bulk Earthworks & Ground Improvement

35-hectare site clearance, grading to design formation levels, dynamic compaction of granular sub-base, dewatering, and temporary haul roads. All earthworks completed in 10 weeks using a fleet of 18 pieces of heavy plant operating double-shift.

Phase 02
Civil Infrastructure & Drainage

Reinforced concrete warehouse slabs (200mm armoured) designed to 50 kN/m² distributed load capacity, storm drainage network, foul drainage, freshwater reticulation, fire-main ring main, and perimeter security road. Concurrent with Phase 01 in separate zones.

Phase 03
Structural Steel Portal Frames

Fabrication and erection of 4 clearspan steel portal frame structures, spans ranging from 36m to 48m, ridge height 12m. Cladding panels, louvers, roof lights, and loading dock canopies erected concurrently as steelwork advanced zone by zone.

Phase 04
MEP, External Works & Commissioning

11kV substation and LV distribution, lighting (LED, 300 lux minimum), VESDA fire detection, ESFR sprinkler system, HVAC to office areas, CCTV and access control, truck yard surfacing, boundary fencing, gatehouse, and landscaping strips. Full commissioning and authority sign-off in final 6 weeks.

Problem & Solution

The Challenge
Extreme Summer Heat & Fast-Track Programme

The project commenced in May 2023 — peak UAE summer. The fast-track 14-month programme meant there was zero float to absorb the mandatory MOHRE midday work ban (June–September) that prohibits outdoor work 12:00–3:00 PM daily. Without a mitigation plan, the programme would slip by 4 weeks minimum.

Our Solution
Double-Shift & Indoor-First Sequencing

ANIB restructured the construction schedule to front-load all outdoor earthworks and infrastructure to the pre-ban period. During the ban months, teams were resequenced to indoor activities: concrete slab pour (early morning), MEP rough-in, steelwork erection in the evening shift. A dedicated welfare team monitored heat stress and hydration throughout. Programme absorbed the ban with only 4 days of net delay.

Fast-Track. Fully Operational.
0
EPC Delivery — Full Scope
0
Industrial Floor Space Delivered
0
Time to First Tenant Occupation
★★★★★
"ANIB's management of a highly complex EPC programme in peak summer conditions was outstanding. They delivered a fully operational 35,000 m² facility in 14 months — something we believed would require at least 18. Their engineering team and site management were first class throughout."
KA
Khalid Al Ansari
CEO, Dubai South Logistics Ltd

Project Data Sheet

Project TypeIndustrial Logistics & Warehousing Campus
LocationDubai South Free Zone, Dubai, UAE
Total GFA (Warehouses)35,000 m² (4 independent units)
Warehouse Spans36m – 48m clearspan, 12m eave height
Floor Loading50 kN/m² distributed; 80 kN point load
Structural SystemHot-rolled steel portal frames, RC hardstanding
Electrical Supply11kV dedicated substation, 3MVA capacity
Fire SuppressionESFR sprinkler system, VESDA detection
Contract TypeEPC, Lump Sum
Contract ValueAED 38,000,000
Construction Period14 months (May 2023 – Jul 2024) — fast-track
HandoverQ1 2024 (July 2024)
Regulatory AuthorityDubai South / JAFZA / DEWA
Services ProvidedEPC — Civil, Structural, MEP, Infrastructure
HSE PerformanceZero LTI — full programme duration